First of all, the maintenance of the control room of the concrete mixing plant

 

In winter, it is not only the external parts that are easily damaged, the control room also needs to be carefully maintained

 

1. If the temperature is too low, please turn on the air conditioner first, and turn it on after the indoor temperature is above 15°C (to protect the hard disk).

 

2. The industrial computer must be connected to the UPS and ensure that the UPS works normally, so as not to damage the hard disk due to a sudden power failure, resulting in data loss or even failure to start the host.

 

3. Back up data once a month to avoid unrecoverable data loss in unexpected situations.

 

Secondly, the maintenance of the air circuit of the air compressor of the concrete mixing station

 

The production line often has the problem of excessive or slow loading of aggregates and powders. The general reason is that the air circuit of the air compressor needs to be maintained.

 

1. Change the air filter element of the air compressor in time, and pay attention to dust prevention (remember to replace the oil of the air compressor itself)

 

2. The air compressor, air storage tank, triple air source, and pressure reducing valve must be drained frequently [three times a day]

 

3. The air source triple unit ensures that the turbine oil is sufficient.

 

Furthermore, the maintenance of the transmission system of the concrete mixing plant

 

The efficiency of the production line is reduced and there is noise. In fact, it is the "maintenance" signal sent by the transmission system.

 

1. To replace the gears of each reducer, the maintenance cycle is 1000h/half a year (it needs to be replaced within 50h-100h of the first warranty).

 

2. Lubricate the transmission structures: main engine, screw reducer (both upper and lower ends need to add butter).

 